|

Consequent
to the in-principle indicative approval of the State Government
of Perak of the Lekir Coastal Development Project ("Lekir
Coastal Project") in 1996, two companies were formed by three partners to promote, develop and implement
the Lekir Coastal Project, which comprised two related developments:
Desa Kilat Sdn. Bhd. (DKSB)
The
promotion and development of the Lekir Coastal Project
comprising the reclamation of land from the sea in the
form of islands and the sale of these islands. Total area
available for reclamation was 20,000 acres.
Lekir Bulk Terminal Sdn. Bhd. (LBT)
The
promotion and development of a very deep water bulk terminal,
complementary in nature to LMT and the Lekir Coastal Project.
The founding promoters of DKSB and LBT were:
Perbadanan
Kemajuan Negeri Perak
Halim Rasip Holdings
Sdn. Bhd.
Malakoff Berhad
The
current shareholders of DKSB and LBT are:
DKSB
The
founding promoters
LBT
Integrax Berhad
Malakoff Berhad
DKSB
commenced reclamation of the First Island (of 325 hectares)
in July 1997 in waters of depth 0.5m to 2.0m ACD. The scope
of works included reclamation of land, slope protection
and the construction of a bunded enclosed body of water.
To date, this represents the largest reclamation project,
by area, in Malaysia.
The
First Island was completed on 31 August 1999, and was handed
over to its purchasers, TNB Janamanjung Sdn. Bhd. for the
purposes of construction and operation of a coal-fired 2,100
MW Power Station, and LBT, for the purposes of its very
deep water bulk terminal, pursuant to Site Acquisition Agreements
executed in January 1999.
| DKSB
Project Team |
| Project
Directors - First Island |
: |
Harun
Halim Rasip and Ahmad Jauhari Yahya |
| Employer's
Representative |
: |
Terra
Geotechnics Sdn. Bhd. |
| Contractor
|
: |
Van
Oord ACZ |
|
LBT
executed a Jetty Terminal Usage Agreement with TNB Janamanjung
Sdn. Bhd. in August 1999 for the provision of coal unloading
and delivery services to the Power Station, thus securing
an anchor customer. LBT commenced
the construction of Phase I of the dry bulk terminal in May
2000, comprising berths able to accommodate Capemax and
Panamax vessels with water depths alongside of 20m ACD,
a 2,000m trestle, 2 grab discharge cranes, mechanised handling
equipment and controls and appropriate onshore support facilities.
In
30 June 2000, LBT achieved financial close with the issue
of an RM445 million Serial Bond rated AA3 by Rating Agency
Malaysia Bhd. on a non-recourse project finance basis.
| LBT
Project Team (Phase I) |
|
Project Director |
: |
Harun
Halim Rasip |
| Employer's
Representative |
: |
Amin
Halim Rasip |
| Financial
Advisors |
: |
HSBC
Investment Bank Plc |
| Lead
Manager |
: |
HSBC
Bank Malaysia Bhd. |
| Legal
Advisors |
: |
Wong
& Partners |
| Insurance
Advisors |
: |
Bradstock
Insurance Brokers Sdn. Bhd. |
| Engineering
Consultants |
: |
GHD
Pty Ltd, Australia |
| Contractor |
: |
Leighton
Contractors (Malaysia) Sdn. Bhd. with sub-contractor
Koch Transporttechnik GmbH |
|
|